掃碼下載APP
及時(shí)接收考試資訊及
備考信息
安卓版本:8.7.30 蘋果版本:8.7.30
開發(fā)者:北京正保會計(jì)科技有限公司
應(yīng)用涉及權(quán)限:查看權(quán)限>
APP隱私政策:查看政策>
HD版本上線:點(diǎn)擊下載>
ELEVATING BOTTLENECKS
The next step is therefore to try and elevate the capacity of the bottlenecks. This is not easy without spending money, but observation shows that, at times, the bottleneck machines are sometimes still idle, despite the labelling system giving priority to the parts that have to be ready to go through the bottleneck machines. This is partly because workers are taking their breaks before getting the machines running again, and partly because they have left the machines unmanned because they have been called away to work on another (non-bottleneck) machine. Both of these absences result in the machines becoming idle. At this point, Alex learns an important lesson: an hour lost on a bottleneck machine is an hour lost for the entire system. This hour can never be recouped. It is pointless to leave a bottleneck machine unmanned in order to go and load up a non-bottleneck machine because there is spare capacity on the non-bottleneck machine anyway. It doesn’t matter if it’s not running for a bit. But it does matter in the case of the bottleneck. From this point onwards, the two bottlenecks are permanently manned and permanently running. Their capacity is elevated this way, along with another few changes that are implemented.
THE NEED TO ACCEPT IDLE TIME
At this point, Alex and his team think they have saved the factory, and then suddenly they find that new bottlenecks seem to be appearing. Parts with green labels on are not being completed in sufficient quantities, meaning that final assembly of the company’s products is again not taking place, and orders are being delayed again (because final assembly of products requires both bottleneck and non-bottleneck parts). Alex calls Jonah in a panic and asks for help. Jonah soon identifies the problem. Factory workers are still trying to be as efficient as possible, all of the time. This means that they are getting their machines to produce as many parts as possible, irrespective of the number of parts that can actually be processed by the bottleneck.
Jonah begins to explain, labelling a bottleneck machine as X and a non-bottleneck machine as Y. Some products may not need to go through X, he says, but that doesn’t mean that workers should make as many parts as the machines can produce, just to keep the machine’s efficiency rate looking good. Y parts should only be produced to the extent that they can be used in the assembly of finished goods, and the production
of these is constrained by their need for bottleneck parts too. Any excess Y parts will simply go to the warehouse and be stored as finished goods, ultimately becoming obsolete and having to be written off at a substantial cost.
As for those products that do need to go through X, they may, for example, go from Y to Y to X to Y (as there are numerous steps involved in the production process). But if the capacity of the first Y machine is far higher than the capacity of the next Y machine, and it processes excessive X parts, another bottleneck may look like it has appeared on the second Y machine because so many red labelled parts are being fed through that it never gets to process the green ones, which are also necessary for final assembly. Suddenly Alex realises that all machines must work at the pace set by the bottleneck machines, just like the boys on the hike that had to walk at the pace of the slowest walker.
Consequently, Alex realises that it is really important to let Y machines and workers sit idle when they have produced to the capacity of the bottleneck machines. By definition, they have spare capacity. It’s not only wasteful to produce parts that are not needed or cannot be processed; it also clogs up the whole system and makes it seem as if new bottlenecks are appearing. This idea of idle time not only being acceptable but also being essential flies in the face of everything that is believed at the time and, yet, when you understand the theory of constraints, it makes perfect sense. A balanced factory is not efficient at all; it is very inefficient because different machines and processes have different capacities, and if machines that have spare capacity are working 100% of the time, they are producing parts that are not needed. This is wasteful, not efficient. As evidenced in the novel, inventory goes up and throughput goes down. Alex is quick to resolve the problem and get things running smoothly again.
THROUGHPUT AND JUST-IN-TIME
Given that producing excess inventories both pushes costs up and prevents throughput, it becomes obvious that throughput accounting and just in time operate very well together. This becomes clear towards the end of the novel when UniCo secures even more orders by reducing its delivery time dramatically. It is able to do this by adopting some of the principles of just-in-time.
First, Alex reduces batch sizes substantially. For those unfamiliar with throughput accounting and just-in-time, it can be hard to get past the idea that if batch sizes are halved, financial results may still improve. The novice believes that if batch sizes are halved, costs must go up, because more orders are needed, more set ups are needed, more deliveries are needed, and so on... and surely these costs must be high? But the fact is – as proved in the novel – inventory costs are also halved and, even more importantly, lead time is halved, which in this case gives UniCo a competitive advantage. Throughput increases dramatically because of increased sales volumes. These increased sales volumes also led to a significantly lower operating cost per unit, which, along with the reduced inventory costs, more than makes up for increase in the other costs. Given that there is spare capacity for all of the non-bottleneck machines
anyway, if the number of set ups for these is increased, no real additional cost arises because there is idle time. As Jonah says: ‘An hour saved on a non-bottleneck resource is a mirage.’
CONCLUSION
It is not possible, within the space of a few pages, to convey everything that The Goal has to say. To think that I could do so would be an insult to the authors of this 273-page novel. Nor is the theory contained within the novel beyond questioning and criticism; but this article was not meant as a critique.
Hopefully, however, I have told you enough to convince you that this book is worth reading should you have a couple of days to spare sometime. I haven’t, after all, told you the ending... Also, you should now have an understanding of the background to my second article, which you will find in the next issue of Student Accountant.
Written by a member of the Paper F5 examining team
Page 1 2 The original article>>
歷年樣卷
考試大綱
詞匯表
報(bào)考指南
考官文章
思維導(dǎo)圖
安卓版本:8.7.30 蘋果版本:8.7.30
開發(fā)者:北京正保會計(jì)科技有限公司
應(yīng)用涉及權(quán)限:查看權(quán)限>
APP隱私政策:查看政策>
HD版本上線:點(diǎn)擊下載>
官方公眾號
微信掃一掃
官方視頻號
微信掃一掃
官方抖音號
抖音掃一掃
Copyright © 2000 - m.galtzs.cn All Rights Reserved. 北京正保會計(jì)科技有限公司 版權(quán)所有
京B2-20200959 京ICP備20012371號-7 出版物經(jīng)營許可證 京公網(wǎng)安備 11010802044457號