你好;? 按照完工進度比例來結(jié)轉(zhuǎn)收入和成本的??
2023 02/22 16:15
![](http://member.chinaacc.com/homes/resources/images/home/avatar/3.jpg)
84785043 ![](/wenda/_nuxt/img/reply1.d92ea43.png)
![](/wenda/_nuxt/img/reply1.d92ea43.png)
2023 02/22 16:16
如果沒有收入呢
![](http://member.chinaacc.com/homes/resources/images/home/avatar/3.jpg)
84785043 ![](/wenda/_nuxt/img/reply1.d92ea43.png)
![](/wenda/_nuxt/img/reply1.d92ea43.png)
2023 02/22 16:16
新的項目,只是發(fā)生了一些間接費呢
![](https://pic1.acc5.cn/009/94/28/94_avatar_middle.jpg?t=1714035575)
meizi老師 ![](/wenda/_nuxt/img/reply2.28c7604.png)
![](/wenda/_nuxt/img/reply2.28c7604.png)
2023 02/22 16:20
你好;? ? ?才開始 ; 老準則用工程施工科目 ;? 新準則用? ?合同履約成本? ?
![](http://member.chinaacc.com/homes/resources/images/home/avatar/3.jpg)
84785043 ![](/wenda/_nuxt/img/reply1.d92ea43.png)
![](/wenda/_nuxt/img/reply1.d92ea43.png)
2023 02/22 16:22
嗯嗯,我想問的是,剛開始的項目,像發(fā)生的這些間接費用,月末是不是不用結(jié)轉(zhuǎn)
![](https://pic1.acc5.cn/009/94/28/94_avatar_middle.jpg?t=1714035575)
meizi老師 ![](/wenda/_nuxt/img/reply2.28c7604.png)
![](/wenda/_nuxt/img/reply2.28c7604.png)
2023 02/22 16:27
你好;? ? ?是的;暫時不結(jié)轉(zhuǎn)哈? ?